Week of 08/26/07
Back to Progress

Ductwork installed under existing floor slab to
f eed the East Addition.

Depressed slab (for ductwork) complete at East Addition.

Conduits installed from transformer into West
Addition for Electric Feeders


Structural steel erection complete at East Addition.
Bar joists to follow.

Storm sewer structures at parking lot being installed.
|