Union Rural
Electric
Week of 08/13/07
Back to Progress

North addition underground plumbing, foundations,
and
slab complete

East addition underground plumbing and foundations
complete.
Slab has just been poured, and is being finished

Hydronic piping has been extended from attic space
of existing building to the North Addition

Electrical conduit, sheet metal ductwork, and hydronic
piping is
being installed in the existing attic space

West Addition underground plumbing, foundations,
and
slab complete
|